Requirements:
- Must be used with an equal or greater amount of soffit vent.
- Compressor pressure should be between 80 psi and 100 psi, depending on conditions.
- Xtractor Vent XLP Turbo installs on pitches 3/12 to 16/12.
- Use 1 ¾” collated nails provided to assure proper penetration into the sheathing (3/4” or completely through the sheathing).
-
Use with standard 12” wide cap shingles.
-
If ridge beam is wider than 2", call Customer Service at 800-346-7655.
|
|
|
Step 1: Cut a slot in plywood along the roof ridge 1 1/2" wide (3/4" on each side). If ridge beam is present, cut slot 3/4" wide on each side of ridge beam. Allow for a closed area of sheathing 12" at both ends of ridge. |
|

|
|
|
|
|
Step 2:Place beginning female end of vent 1" in from gable end and use centering line for proper alignment along peak. Fasten using at least two nails at each end and in middle of roll in nail line area (1 3/4" minimum nail length) spacing approximately every 12 inches. More nails may be required on steeper slopes to seat properly. Continue installing additional rolls as needed along ridge sliding female end over male end, aligning using centering line. When reaching the other end, cut vent roll to 1” from the gable end and nail in place. End plugs are provided every 6” on the underside of the product.
|
|

|
|
|
|
|
Step 3: Place first cap shingle over vent so that it overhangs at least 1" over end of vent roll. Install with 1 3/4" nails provided in nail line area as you work your way down the roof. Cut last cap shingle so that it overhangs vent 1" at other gable end.
|
|
 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|