Requirements:
- Must be used with an equal or greater amount of soffit ventilation
- Installs on pitches 3/12 to 16/12
- Use with standard 12” wide cap shingles
- Use 2-1/2” minimum nails to assure penetration of 3/4” into sheathing or completely through the sheathing
|
|
|
Step
1: Cut a slot in plywood
along roof ridge 2" wide
(1" on each side). If
ridge beam is present,
cut slot 1" wide on each
side of ridge beam.
Allow for a closed area
of sheathing 12" at both
ends of ridge. |
|

|
|
|
Step 2:
Place first piece of vent with
female end 1" in from gable end
and use centering line for proper
alignment along peak. Fasten
using at least two nails at each
end and in middle of section in
nail line area (2-1/2" minimum
nail length). More may be
required on steeper slopes to seat
properly. Continue installing
additional pieces along ridge
sliding female end over male end,
aligning using centering line.
NOTE: In cold weather, allow a
1/8" gap between vent sections
for expansion. |
|

|
|
|
Step 3: When reaching the other
end, the last vent section
may need to be cut to
length. End plugs are
provided every 12" on
underside of the product.
Measure amount needed
to install to within 1" of
the gable end. Cut that
length in from end of
vent section and flip
around so that end plug
is at gable end. Allow
male tab from previous
piece to slide under last
piece and nail in place. |
|

|
|
|
Step 4: Place first cap shingle over
vent so that it overhangs at
least 1" over end of vent
section. Install with 2-1/2"
nails in nail line area as you
work your way down the
roof. Cut last cap shingle so
that it overhangs vent 1" at
other gable end. |
|
 |
| |
|
|
|
|
Helpful Hints:
- Optionally, you may install cap shingles on each piece as you go along, taking care to assure proper alignment.
- If installing on dimensional or architectural shingles on new construction, leave felt underlayment about 6" long at roof ridge and
fold back under the vent so that vent is essentially installed on top of felt over the shingles. If re-roofing, caulk between low areas of
shingle and baffle of vent after installation.
- Lines across top of product indicate where the end plugs are on the underside (every 12"). There is no need to flip the last piece if
you measure and plan ahead to install on an even foot increment.
- The nail line area is completely free from obstructions except where the end plugs are (unlike other sectional ridge vents that can have
nails deflect off of supports). By using the end plug indicators on top of product, you can easily avoid nails through the end plugs.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|